Main Library Construction Timeline

Construction Timeline

Completed Building Program. 2007

2007

Decision To Build New Main Library at Goodwood. 2007

2007

Selection of Architect. December 2007

12/01/2007

Concept Design Phase. Spring 2008

03/2008

Design Development Continues

08/2008 - 03/2009

Public Design Charette. August 2008

08/2008

Schematic Design. Spring 2009

04/2009

Design Development Presentation. May 2010

05/2010

Construction Bids. August 2011

08/2011

720 Days Alloted For Construction of Phase I. Main Library Building.

10/19/2011 - 10/13/2013

Break Ground. October 19, 2011

10/19/2011

Topping Off. July 11, 2012

07/11/12

Furniture Installation. September/October 2013

09/2013 - 10/2013

Major Completion Scheduled for September 2013

09/2013

Move The Collection and Move In. October/November 2013

10/2013 - 11/2013

Demolish Old Main Library & Construct Parking Lot. Nov 2013-Jan 2014 (Estimated)

11/2013 - 01/2014

Soft Opening

11/15/2013

Construct Rest of Shared Plaza.

02/2014 - 03/2014

Grand Opening. Spring 2014

04/2014