Again, attempting to compress the hardening due to higher trust in automation and leveraging Flyway implementation.
Again, attempting to compress the hardening due to higher trust in automation and leveraging Flyway implementation.
November 5, 2019 - November 8, 2019
% complete
Upgrade team to finish Installation script for TC2
November 14, 2019
% complete
No more planned changes to be made to the product. Only critical/blocker bug fixes and security fixes are allowed, as part of hardening.
Any changes needed for the release is made in DEFAULT, and only merged to RELEASE branch upon GREEN build.
November 14, 2019
% complete
No more planned changes to be made to the product. Only new bugfixes and security fixes are allowed, as part of hardening.
RC0 Tag: First test cycle env. (plain), and basis for Upgrade Script.
November 15, 2019 - November 21, 2019
% complete
RC0 ready morning 13th Nov
BQ env from Flyway scripts ("plain") ready by 14th.
Upgrade script: 3d from RC0, Friday 15th
Docker images with base version ready before 15th.
CM deploying envs based on upgraded dockers from Monday 18th
Start TC1 from Wed 20th.
November 15, 2019 - November 19, 2019
% complete
November 19, 2019 - December 13, 2019
% complete
November 20, 2019 - November 28, 2019
% complete
Connect with 2-3 customer projects with EC-12.1-SP01 systems that can be used to test installation of 12.2 upgrade script.
Ownership to be placed with Upgrade team.
November 21, 2019 - 1 day
% complete
Exploratory testing, for all PRD and PRS who can participate.
Upgraded 12.2.RC0 environment.
November 22, 2019 - November 27, 2019
% complete
Testing on Upgrade environment
Manual testing:
- Execution of all the ECPTs related to the planned scope
- Critical regression tests (not yet automated)
Automated Tests (ALL)
November 22, 2019 - November 28, 2019
% complete
Fixing bugs found during TC1, or critical/blocker bugs accepted passed the Scope Work Done point.
November 22, 2019 - November 27, 2019
% complete
November 28, 2019
% complete
November 28, 2019
% complete
Allow for Upgrade team to incorporate the db changes into the upgrade script that will be used for TC2
November 29, 2019 - December 3, 2019
% complete
Ready by morning KL next day.
November 29, 2019 - December 2, 2019
% complete
November 29, 2019 - December 5, 2019
% complete
FRMW Team, Testers need to test the EC Tools: EC SDK, EC Assembly tool.
December 4, 2019 - December 9, 2019
% complete
Manual testing:
- ALL not-yet-automated Regression Tests
- Failed and Fixed issues in TC1
- Test blocked/NA/not completed in TC1
- (N/A) Retest scope issues having db upgrade impact area info in JIRA
- Exploratory Testing of key functional areas
Automated testing (ALL):
- Functional UI regression/scenarios tests
- Functional Issue tests
- Screen/Smoke tests (IUD)
- Performance tests
- Security (Veracode Scan)
- Scenario Tester (Revenue)
- Run automated regression tests on Imported DB
Scope:
- Testing on Upgrade environment
- Manual Test Execution on Upgrade and Plain Environment
December 4, 2019 - December 10, 2019
% complete
Fixing bugs found in TC2
December 5, 2019 - 1 day
% complete
Second Bug Quest, on an Upgraded environment
December 10, 2019
% complete
December 11, 2019 - December 17, 2019
% complete
Final review and generation of PDFs
December 11, 2019 - December 13, 2019
% complete
December 11, 2019 - December 12, 2019
% complete
December 16, 2019 - 4 days
% complete
@until 11am CET
Last test cycle, based on final RC, validating blocker fixes from TC2.
December 16, 2019 - 4 days
% complete
@until 11am CET
Exploratory Testing of Critical Path scenarios, sign-off that all key features work as expected.
December 19, 2019
% complete
@11am CET
December 20, 2019
% complete
Our goal is to release as short as possible after the GO/NO-GO decision.
November 11, 2019 - November 15, 2019
% complete
Out of scope:
"Product area specific upgrade impact" section
Verification by Upgrade Team and Release Team.
How to Upgrade document:
http://ecpedia.eu.tieto.com/display/RD121/How+to+Upgrade+from+EC-12.1
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
November 11, 2019 - November 14, 2019
% complete
Installation Guide document:
http://ecpedia.eu.tieto.com/display/RD122/EC-12.2+-+Installation+Guide
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
November 18, 2019 - December 5, 2019
% complete
November 18, 2019 - December 5, 2019
% complete
Release Details document: http://ecpedia.eu.tieto.com/display/RD122/EC-12.2+-+JIRA+Filters+for+Release+Details
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE122/EC-12.2+Documentation+Scope
November 21, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Offline Help to be generated in Bug Quest 1 env (EC screen).
All product teams need to verify the Offline Help (BF documents) throughout TC1 and TC2.
December 5, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Offline Help to be generated in Bug Quest 2 or TC2 env (EC screen).
Fixes of Offline Help in TC1 will be available in TC2 Offline Help.
All product teams need to verify the Offline Help (BF documents) throughout TC1 and TC2.
December 6, 2019
% complete
Preparation and verification by POs & PMs.
Known Limitations (in the Release Notes):
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Notes#EC-12.1-SP01-ReleaseNotes-KnownLimitations
December 6, 2019 - December 10, 2019
% complete
Upgrade Impact section in HowTo Upgrade document:
http://ecpedia.eu.tieto.com/display/RD121/How+to+Upgrade+from+EC-12.1
December 9, 2019 - December 10, 2019
% complete
Responsibility: POs and Release Team (final verification)
Release Details document: http://ecpedia.eu.tieto.com/display/RD122/EC-12.2+-+JIRA+Filters+for+Release+Details
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE122/EC-12.2+Documentation+Scope
December 9, 2019 - December 13, 2019
% complete
Highlights document (in the Release Notes):
http://ecpedia.eu.tieto.com/display/RD122/EC-12.2+-+Release+Notes
Content refinement from Release Scope page:
http://ecpedia.eu.tieto.com/display/RE122/EC-12.2+Release+Scope
Responsibility: Release Team
December 11, 2019
% complete
Preparation, modifications and verification by POs & PMs.
Technical Overview document:
http://ecpedia.eu.tieto.com/display/RD122/EC-12.2+-+Technical+Overview
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE122/EC-12.2+Documentation+Scope
December 11, 2019 - December 17, 2019
% complete
December 16, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Teams need to review again the affected Offline Help (which was fixed in TC2)
Release Team briefly scan through the final Offline Help before upload to ECUC.
December 16, 2019
% complete