Multi-lingual English/German microsite that will have its own CAE sub-domain.
Multi-lingual English/German microsite that will have its own CAE sub-domain.
19 August 2019
% complete
Official project kick-off!
August 19, 2019 12:01 AM - 3 days
% complete
Discovery phase based on provided requirements in order to find the best solution and identify any potential issues.
August 22, 2019
% complete
Acceptance of proposed solution and acceptance of any identified issues based on the original requirements.
*The selected sub-domain should be registered at this time to avoid any possible delays for launch.
August 22, 2019 12:01 AM - August 28, 2019
% complete
CMS & Site setup based on requirements and the approved solution. This includes the micro-site server, sub-domain CMS and required resources (templates, assets, and dependencies) * Selection of existing CAE templates should be completed during this time.
August 29, 2019
% complete
Deadline for all content submission, English and German, including all required images, related downloads and other assets.
August 29, 2019 - September 8, 2019
% complete
Menu creation and integration of both English and German content into selected existing CAE page templates. This includes the new contact form for the site.
September 9, 2019 - September 11, 2019
% complete
CAE to QA the complete solution and submit any required updates/changes.
September 12, 2019
% complete
Deadline to submit any updates/changes, content or functional for the micro site.
September 12, 2019 - September 12, 2019
% complete
Integration of updates/changes submitted during the QA phase of the project.
September 13, 2019
% complete