PharmaCann: Post-Deal ERP Implementation Timeline

Outlines a high level post-deal implementation approach for PharmCann

NAV-NAV Implementation

December 9, 2019

Finance

January 1, 2020 - 4 weeks

February 1, 2020 - 2 weeks

February 18, 2020 - 2 weeks

February 26, 2020

February 26, 2020

February 26, 2020

February 26, 2020

September 30, 2020

Master Data

January 6, 2020 - 3 weeks

January 27, 2020 - 2 weeks

February 1, 2020

February 1, 2020

February 1, 2020

February 1, 2020

February 10, 2020 - 2 weeks

Retail

Sourcing & Procurement

February 25, 2020 - 3 weeks

March 19, 2020 - 2 weeks

April 2, 2020 - 2 weeks

April 8, 2020

April 8, 2020

April 8, 2020

Production

May 28, 2020 - 4 weeks

June 27, 2020 - 4 weeks

July 28, 2020 - 6 weeks

August 9, 2020

Cultivation

June 30, 2020 - 4 weeks

July 30, 2020 - 4 weeks

September 1, 2020 - 26 days

Warehousing & Distro

February 9, 2020 - 4 weeks

March 8, 2020 - 4 weeks

April 6, 2020 - 6 weeks

Accounts Payables

January 20, 2020 - 4 weeks

February 19, 2020 - 4 weeks

March 22, 2020 - 6 weeks

Materials Resource Planning

October 14, 2020

NAV Config

January 28, 2020

April 1, 2020