Again, attempting to compress the hardening due to higher trust in automation.
Again, attempting to compress the hardening due to higher trust in automation.
May 17, 2019
% complete
No more planned changes to be made to the product. Only new bugfixes and security fixes are allowed, as part of hardening.
RC0 Tag: First test cycle env. (plain), and basis for Upgrade Script.
May 17, 2019
% complete
No more planned changes to be made to the product. Only critical/blocker bugfixes and security fixes are allowed, as part of hardening.
Any changes needed for the release is made in DEFAULT, and only merged to RELEASE branch upon GREEN build.
May 20, 2019 - June 17, 2019
% complete
May 20, 2019 - May 29, 2019
% complete
May 24, 2019 - May 29, 2019
% complete
May 30, 2019 - 1 day
% complete
Exploratory testing, for all PRD and PRS who can participate.
Plain SP01 environment. Upgraded, if possible.
May 31, 2019 - June 5, 2019
% complete
Testing on Upgrade environment
Manual testing:
- Execution of all the ECPTs related to the planned scope
- Critical regression tests (not yet automated)
Automated Tests (ALL)
May 31, 2019 - June 6, 2019
% complete
Fixing bugs found during TC1, or critical/blocker bugs accepted passed the Scope Work Done point.
June 4, 2019
% complete
Allow for Upgrade team to incorporate the db changes into the upgrade script that will be used for TC2
June 5, 2019 - June 7, 2019
% complete
June 6, 2019
% complete
June 10, 2019 - June 14, 2019
% complete
Connect with 2-3 customer projects with EC-12.1 systems that can be used to test installation of 12.1-SP01 upgrade script.
Ownership to be placed with Upgrade team.
June 10, 2019 - June 11, 2019
% complete
Ready by morning KL next day.
June 11, 2019 - 1 day
% complete
Second Bug Quest, on an Upgraded environment
June 12, 2019 - June 17, 2019
% complete
June 12, 2019 - June 17, 2019
% complete
Manual testing:
- ALL not-yet-automated Regression Tests
- Failed and Fixed issues in TC1
- Test blocked/NA/not completed in TC1
- (N/A) Retest scope issues having db upgrade impact area info in JIRA
- Exploratory Testing of key functional areas
Automated testing (ALL):
- Functional UI regression/scenarios tests
- Functional Issue tests
- Screen/Smoke tests (IUD)
- Performance tests
- Security (Veracode Scan)
- Scenario Tester (Revenue)
Scope:
- Testing on Upgrade environment
- Manual Test Execution on Upgrade and Plain Environment
June 12, 2019 - June 18, 2019
% complete
Fixing bugs found in TC2
June 18, 2019
% complete
June 19, 2019 - June 25, 2019
% complete
Final review and generation of PDFs
June 19, 2019 - June 21, 2019
% complete
June 24, 2019 - 2 days
% complete
Last test cycle, based on final RC, validating blocker fixes from TC2.
June 24, 2019 - 2 days
% complete
Exploratory Testing of Critical Path scenarios, sign-off that all key features work as expected.
June 26, 2019
% complete
June 27, 2019
% complete
Our goal is to release as short as possible after the GO/NO-GO decision.
May 2, 2019 - May 10, 2019
% complete
Release Scope (Highlights):
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Release+Scope
Responsibility: PMs & POs
May 30, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Offline Help to be generated in Bug Quest 1 or TC1 env (EC screen).
All product teams need to verify the Offline Help (BF documents) throughout TC1 and TC2.
May 31, 2019
% complete
Test Online Help installation by Release Team (1st trial)
June 4, 2019 - June 17, 2019
% complete
Highlights document (in the Release Notes):
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Notes#EC-12.1-SP01-ReleaseNotes-Highlights
Content refinement from Release Scope page:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Release+Scope
Responsibility: Release Team
June 6, 2019 - June 14, 2019
% complete
Release Details document: http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Details
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
June 11, 2019 - June 21, 2019
% complete
Verification by Product Support Team.
Audit: 17th & 18th June
June 11, 2019 - June 14, 2019
% complete
Out of scope:
"Product area specific upgrade impact" section
Verification by Upgrade Team and Release Team.
How to Upgrade document:
http://ecpedia.eu.tieto.com/display/RD121/How+to+Upgrade+from+EC-12.1
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
June 11, 2019 - June 14, 2019
% complete
Installation Guide document:
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1+-+Installation+Guide
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
June 11, 2019 - June 14, 2019
% complete
Upgrade Impact section in HowTo Upgrade document:
http://ecpedia.eu.tieto.com/display/RD121/How+to+Upgrade+from+EC-12.1
June 12, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Offline Help to be generated in Bug Quest 2 or TC2 env (EC screen).
Fixes of Offline Help in TC1 will be available in TC2 Offline Help.
All product teams need to verify the Offline Help (BF documents) throughout TC1 and TC2.
June 17, 2019
% complete
Preparation, modifications and verification by POs & PMs.
Technical Overview document:
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1+-+Technical+Overview
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
June 17, 2019
% complete
Preparation and verification by POs & PMs.
Known Limitations (in the Release Notes):
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Notes#EC-12.1-SP01-ReleaseNotes-KnownLimitations
June 17, 2019 - June 18, 2019
% complete
Responsibility: POs and Release Team (final verification)
Release Details document: http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Details
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
June 24, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Teams need to review again the affected Offline Help (which was fixed in TC2)
Release Team briefly review the final Offline Help before upload to ECUC.
June 24, 2019
% complete
Test Online Help installation by Release Team (2nd trial)
May 17, 2019 - 1 day
% complete
None or very limited capacity from NORWAY residents., due to Christmas and New Year.
May 20, 2019 - 1 day
% complete
May 22, 2019 - 1 day
% complete
May 30, 2019 - 1 day
% complete
June 5, 2019 - 1 day
% complete
June 5, 2019 - June 6, 2019
% complete
Possible whole week off.
June 10, 2019 - 1 day
% complete