1 August 2019 - 1 September 2019
% complete
Collect and review requirements along with any currently available solutions. Define project scope and milestones, and develop project timeline overview.
2 September 2019
% complete
Deadline to approve final requirements
2 September 2019 - 3 weeks
% complete
Development of the NFC Router tool according to predefined requirements and discovery phase. Includes basic standalone QA.
23 September 2019 - 3 weeks
% complete
Development of the NFC Scanner application tool according to predefined requirements and discovery phase. Includes basic standalone QA and testing.
7 October 2019 - 1 week
% complete
Front-end design of the NFC Scanner application tool based on predefined requirements.
14 October 2019 - 3 weeks
% complete
Development of the NFC Command Centre application according to predefined requirements and discovery phase. Includes basic, standalone QA and testing.
27 October 2019 - 3 November 2019
% complete
Front-end design of the NFC Command Centre application based on predefined requirements and discovery phase.
4 November 2019 - 21 days
% complete
End to end QA and testing of the complete solution. Part of this QA period will involve the client's participation.
25 November 2019
% complete
Deadline to submit final changes as part of the end to end QA and testing period.
25 November 2019 - 14 days
% complete
Integration of changes and/or fixes based on the end to end QA and testing results.
9 December 2019
% complete
The complete end to end solution is provided to the client for final acceptance.
9 December 2019 - 14 days
% complete
Client acceptance period and approval for the solution to go live.
Milestone only version of timeline
23 September 2019
% complete
Completion of NFC Router Development
14 October 2019
% complete
Completion of the NFC Scanner Application Development
4 November 2019
% complete
Completion of the NFC Command Centre Application development
24 November 2019
% complete
Completion of the End to End QA & Testing procedures
8 December 2019
% complete
Completion of integration of changes and/or fixes as a result of the QA and testing session.
22 December 2019
% complete
Deadline for client acceptance for go-live.