ERP Implementation for TRC

Main

Phase I: Pre-Project Analysis

Process Benchmarking and Analysis of Implementation Landscape

11/01/2012 - 12/31/2012

Identification of Firm Needs

11/01/2012 - 12/31/2012

Potential Initial Business Process Reengineering

01/01/2013 - 04/30/2013

ERP System Selection

04/01/2013 - 04/30/2013

Phase II: Rally Project Support

Garner Support of Upper Management and End-Users

01/01/2013 - 04/30/2013

Phase III: Pre-Implementation Review

Generate Finalized List of Necessary Portals and Applications

05/01/2013 - 06/30/2013

Develop Documentation for Rules And Best Practices; Begin Training

07/01/2013 - 08/31/2013

Develop Pre-Implementation Plan and Begin Building Infrastructure

09/01/2013 - 10/31/2013

Phase IV: Phased Implementation

Accounting/Finance Application Go-Live

11/01/2013 - 12/31/2013

Post-Go-Live Review, Retesting, and Further Go-Lives

12/31/2013 - 07/31/2014