Macroplanning Plateforme TM

Pilotage du projet

Réunion de lancement

17 September 2017

COPRO#1

10 October 2017

COPIL#1

24 October 2017

COPRO#2

16 November 2017

COPIL#2

28 November 2017

COPRO#3

12 December 2017

COPRO#4

16 January 2018

COPIL#3

30 January 2018

Phase 1 : Etude et méthodologie

Etude préalable : cadrage et faisabilité

18 September 2017 - 31 October 2017

Etude détaillée : fonctionnelle, technique et stratégique

1 November 2017 - 31 January 2018

Phase 2 : Assistance à la mise en oeuvre

Elaboration d'un DCE

1 January 2018 - 31 March 2018

Suivi de la consultation et sélection

1 April 2018 - 30 June 2018

Lancement de la consultation MOE

1 April 2018

Suivi du projet

1 July 2018 - 31 March 2019

Notification du marché MOE

30 September 2018

Recette

1 January 2019 - 31 March 2019

Phase 3 : Assistance au suivi, à l'évaluation et à l'évolution

Transfert de connaissances

30 June 2018 - 30 June 2019

Assistance à l'exploitation

1 April 2019 - 30 June 2019

Prestations transverses

Conduite du changement

31 October 2017 - 30 June 2019

Communication

31 January 2018 - 30 June 2019