Programa de las Actividades

Síntesis de los plazos estimados para la ejecución de las actividades

Proceso Administrativo (Escenario Optimista Moderado)

Approx. 5 October 2017 - Approx. 26 October 2017
Approx. 26 October 2017 - 22 November 2017
Approx. 9 Jan 2018
Approx. 10 Jan 2018 - 22 Nov 2018
Approx. 20 Nov 2018 - 20 Dec 2018
Approx. 15 Mar 2019

Desarrollo de las Actuaciones del Proyecto

Approx. 25 Jan 2018 - 25 April 2018
Approx. 25 Jan 2018 - 25 April 2018
26 April 2018
Approx. 27 April 2018 - 14 July 2018
Approx. 27 April 2018 - 2 Sep 2018
Approx. 2 May 2018 - 30 May 2018
Approx. 30 May 2018 - 11 Jul 2018
Approx. 3 Jun 2018 - 28 Sep 2018
Approx. 12 Jul 2018 - 10 Aug 2018
Approx. 12 Aug 2018 - 30 Aug 2018
12 Aug 2018 - 30 Aug 2018
Approx. 12 Aug 2018 - 31 Aug 2018
Approx. 19 Aug 2018 - 30 Sep 2018
Approx. 16 Sep 2018 - 21 Sep 2018
Approx. 16 Sep 2018 - Approx. 28 Sep 2018
28 Sep 2018
10 Oct 2018

Comercialización y promoción

Approx. 15 Jun 2018 - Approx. 1 Aug 2018
Approx. 31 Jul 2018 - 21 Aug 2018
Approx. 30 Aug 2018 - 30 Sep 2018
16 Sep 2018

Recursos Humanos y Organización del Personal

Approx. 1 April 2018 - 30 April 2018
Approx. 1 May 2018 - 31 May 2018
Approx. 2 Sep 2018 - 28 Sep 2018
26 Sep 2018
Approx. 1 Oct 2018 - 9 Oct 2018
22 Nov 2018