Waktu Penyelesaian Pekerjaan Videotron

Events

Pabrikasi VIdetron (30 hari)

September 25, 2017 - October 24, 2017

Survey Lokasi (4 hari)

October 25, 2017 - October 28, 2017

Konstruksi (14 hari)

October 29, 2017 - November 11, 2017

Pemasangan Kabinet (4 hari)

November 12, 2017 - November 15, 2017

Pemasangan Ornamen (4 hari)

November 16, 2017 - November 19, 2017

Pembuatan Panel Listrik (2 hari)

November 20, 2017 - November 21, 2017

Pembuatan Panel Control (2 hari)

November 22, 2017 - November 23, 2017

Instalasi Listrik dan Jaringan (4 hari)

November 24, 2017 - November 27, 2017

Setting Software (2 hari)

November 28, 2017 - November 29, 2017

Project Commisioning (5 hari)

November 30, 2017 - December 4, 2017

Training (3-5 hari)

December 5, 2017 - December 7, 2017