214 - 11 ARDINGS

Main

Ecotecture Structural engineer and Contractors Timeline

Lead in time 1 Week

07 August 2012 - 14 August 2012

Typical time frame for Ecotecture to start works

Building regulations 1 Month

14 August 2012 - 14 September 2012

Production of Building regulastion information by Structural Engineer, specification by Ecotecture, BCO plan check and schedule of works

Issue for tender and tender period 1 Month

14 September 2012 - 15 October 2012

We would recommend a maximum of four highly recommended contractors we would typically recommend two or three of these four

Tender analysis 2 Weeks

15 October 2012 - 29 October 2012

To help make sense of the different tender figures accounting for differences between the pricing approach of individual contractors

Negotiation and appointment of contractor 1 Week

29 October 2012 - 5 November 2012

Should the project be slightly over budget this is a good time to discuss and negotiate with your preferred contractor clever ways to bring costs down

Contractors lead in time 1 Month

05 November 2012 - 05 December 2012

The contract period would be provided by the contractor as part of the tender process we have given an estimate of how long this may take

Construction Phase 3.5 Months

5 December 2012 - 03/13/2013