FAIRHAVEN

Ecotecture Timeline - Stage D

Lead in time 1 Month

29 May 2012 - 26 June 2012

Typical time frame for Ecotecture to start works

Sketch scheme designs with basic 3d model 1 Month

27 June 2012 - 25 July 2012

These will be in the form of hand drawn sketches and basic 3d models

Pre application advice 2 Weeks

25 July 2012 - 08 August 2012

Dependent on work load of local planning office

Sketch schemes updated and reissued to planning if necessary 2 Weeks

08 August 2012 - 22 August 2012

Dependent on feedback from case officer

Scheme design drawn up onto computer 2 Weeks

22 August 2012 - 05 September 2012

AutoCAD digital floorplans elevations and site plans

Planning documentation developed 1 Week

05 September 2012 - 12 September 2012

Design and access statements and sustainability and planning statements

Planning submitted online 1 Week

12 September 2012 - 19 September 2012

Uploaded via the planning portal Ecotecture will pay the planning fees and forward the cost for the application to you as part of our stage end invoice

Planning determination period 2 Months

19 September 2012 - 14 November 2012

This period can be elongated if the application is called into committee by the planner or local councillor