29 May 2012 - 26 June 2012
% complete
Typical time frame for Ecotecture to start works
27 June 2012 - 25 July 2012
% complete
These will be in the form of hand drawn sketches and basic 3d models
25 July 2012 - 08 August 2012
% complete
Dependent on work load of local planning office
08 August 2012 - 22 August 2012
% complete
Dependent on feedback from case officer
22 August 2012 - 05 September 2012
% complete
AutoCAD digital floorplans elevations and site plans
05 September 2012 - 12 September 2012
% complete
Design and access statements and sustainability and planning statements
12 September 2012 - 19 September 2012
% complete
Uploaded via the planning portal Ecotecture will pay the planning fees and forward the cost for the application to you as part of our stage end invoice
19 September 2012 - 14 November 2012
% complete
This period can be elongated if the application is called into committee by the planner or local councillor