14 May 2012 - 25 June 2012
% complete
25 June 2012 - 16 July 2012
% complete
16 July 2012 - 30 July 2012
% complete
30 July 2012 - 06 August 2012
% complete
06 August 2012 - 13 August 2012
% complete
13 August 2012 - 20 August 2012
% complete
Planning Submission and Registration
20 August 2012 - 15 October 2012
% complete
Determination period with Local Council
15 October 2012 - 29 October 2012
% complete
Production of Building Regulation Information by structural engineer and Ecotecture
29 October 2012 - 26 November 2012
% complete
26 November 2012 - 03 December 2012
% complete
03 December 2012 - 10 December 2012
% complete
Negotiation between Contractor Client and Architect
10 December 2012 - 07 January 2013
% complete
This is a typical lead in time we have provided for estimation purposes
07 January 2013 - 01 April 2013
% complete
Ground works super structure and weather proofing of extension including additional services if required
01 April 2013 - 24 June 2013
% complete
Knocking through into the existing ground and first floor Internal finishes & Retrofit measures