Holly Cottage

Ecotecture timeline

Lead in time 6 Weeks

14 May 2012 - 25 June 2012

Suvey drawings and scheme design 3 Weeks

25 June 2012 - 16 July 2012

Pre application advice from planning department 2 Weeks

16 July 2012 - 30 July 2012

Feedback from planning incorporated into scheme 1 Week

30 July 2012 - 06 August 2012

Scheme onto computer 1 Week

06 August 2012 - 13 August 2012

Planning submission 1 Week

13 August 2012 - 20 August 2012

Planning Submission and Registration

Planning determination 2 Months

20 August 2012 - 15 October 2012

Determination period with Local Council

Building regulations 2 Weeks

15 October 2012 - 29 October 2012

Production of Building Regulation Information by structural engineer and Ecotecture

Issue to tender 1 Month

29 October 2012 - 26 November 2012

Tender analysis 1 Week

26 November 2012 - 03 December 2012

Tender negotiation 1 Week

03 December 2012 - 10 December 2012

Negotiation between Contractor Client and Architect

Contractors lead in 1 Month

10 December 2012 - 07 January 2013

This is a typical lead in time we have provided for estimation purposes

Construction Phase 1 3 Months

07 January 2013 - 01 April 2013

Ground works super structure and weather proofing of extension including additional services if required

Construction Phase 2 3 Months

01 April 2013 - 24 June 2013

Knocking through into the existing ground and first floor Internal finishes & Retrofit measures