26 March 2012 - 07 May 2012
% complete
Ecotectures lead in to project start.
07 May 2012 - 28 May 2012
% complete
Estimate period for design stage.
28 May 2012 - 04 June 2012
% complete
Typically feedback occurs during the design stage and towards the end.
04 June 2012 - 11 June 2012
% complete
Digitising scheme design ready for submission.
11 June 2012 - 18 June 2012
% complete
Planning Submission and Registration
18 June 2012 - 13 August 2012
% complete
Determination period with Local Council
13 August 2012 - 27 August 2012
% complete
Production of Building Regulation Information by structural engineer and Ecotecture
27 August 2012 - 24 September 2012
% complete
24 September 2012 - 01 October 2012
% complete
01 October 2012 - 08 October 2012
% complete
Negotiation between Contractor Client and Architect
08 October 2012 - 05 November 2012
% complete
This is a typical lead in time we have provided for estimation purposes
05 November 2012 - 28 January 2013
% complete
Ground works super structure and weather proofing of extension including additional services if required
28 January 2013 - 25 March 2013
% complete
Knocking through into the existing ground and first floor Insulation to loft New velux or sunpipes and new internal finishes