TW Workpackage III, Q3 15 with 3.5 devs on HVI

TW Testing

Testing by TW team

Defects & Quotation

August 31, 2015 - September 11, 2015

Test Assistance (UAT)

August 31, 2015 - December 18, 2015

Migration & Bill Runs

September 14, 2015 - September 25, 2015

Gap Site Handling

September 28, 2015 - October 9, 2015

EDI / HVI Testing

November 9, 2015 - December 11, 2015

Irish Tester?

TW

Code Review

August 12, 2015 - August 13, 2015

Martin, Karl-Heinz, Nico, 2x Infonova Sr. Dev

Defects & Quotation

August 17, 2015 - August 28, 2015

Karl-Heinz, Alex, M

With UI? 8pd more

BF REQ Call

August 17, 2015

KH

Kickoff call

August 19, 2015

N, M, Graeme, Daniel,

Architecture Review

August 25, 2015

Dirk, M, KH, N

Notify CMA

August 31, 2015

Migration & Bill runs

August 31, 2015 - September 11, 2015

Martin, Alex
Check if migration at start or at end

Deployment BF & Migration

September 11, 2015

Martin/Alex

Gap site handling

September 14, 2015 - September 25, 2015

M, (KH)

Training

September 14, 2015

Chloe

(Replace BI)

September 14, 2015 - September 18, 2015

If Tareks tool not working M

Deployment Backcalculation

September 25, 2015

Martin/Alex

Reports & Analytics

September 28, 2015 - October 23, 2015

Arijit

HVI/ EDI

October 19, 2015 - October 23, 2015

KH, Nico
2 days workshop & planning

EDI (PO missing)

October 26, 2015 - November 6, 2015

Alex team

HVI

November 9, 2015 - December 4, 2015

KH,A, M, (Inf)

Deployment HVI

November 27, 2015

Sprints

TW Sprint 1

August 17, 2015 - August 28, 2015

Bugfixing & Quotation

TW Sprint 2

August 31, 2015 - September 11, 2015

System Baseline & Back Calculation

TW Sprint 3

September 14, 2015 - September 25, 2015

Deployment, Back calculation & Impex

HVI

October 19, 2015 - October 23, 2015

KH, Nico, DIrk

TW Sprint 4

October 26, 2015 - November 6, 2015

HVI

TW Sprint 5

November 9, 2015 - November 20, 2015

HVI

TW Sprint 6

November 23, 2015 - December 4, 2015

HVI/EDI