290 - PREVETTS MAIN HOUSE

Ecotecture Structural engineer and Contractors Timeline

Lead in time 6 Weeks

04/28/2014 - 06/09/2014

Typical time frame for Ecotecture to start works

Building regulations 1 Month

06/09/2014 - 07/07/2014

Production of Building regulation information by Structural Engineer, specification by Ecotecture, BCO plan check and schedule of works

Issue for tender and tender period 1 Month

07/07/2014 - 08/04/2014

We would recommend a maximum of four highly recommended contractors we would typically recommend two or three of these four

Tender analysis 2 Weeks

08/04/2014 - 08/18/2014

To help make sense of the different tender figures accounting for differences between the pricing approach of individual contractors

Negotiation/appointment of contractor 1 Week

08/18/2014 - 08/25/2014

Should the project be slightly over budget this is a good time to discuss and negotiate with your preferred contractor clever ways to bring costs down

Contractors lead in time 1 Month

08/25/2014 - 09/22/2014

The contract period would be provided by the contractor as part of the tender process we have given an estimate of how long this may take