Setup Hosted Exchange Server

1/1/2011 - 1/7/2011

Upgrade Internal Hardware

1/7/2011 - 1/21/2011

IT Training Courses for Cathy

2/1/2011 - 7/1/2011

Setup Hosted Newsletter Solution

2/1/2011 - 3/1/2011

Setup VoIP for External Phone Calls

2/1/2011 - 2/21/2011

Create HTML Template for Newsletter

2/15/2011 - 3/15/2011

Setup Audio Teleconferencing Facilities

2/15/2011 - 2/28/2011

Setup a Videoconference Facility

3/1/2011 - 4/1/2011

Start Using Hosted Newsletter Solution

4/1/2011

Setup Online Survey Tool

4/1/2011 - 5/1/2011

Setup Webinar Functionality

4/15/2011 - 7/1/2011

Overhaul Current Web site

5/1/2011 - 9/1/2011

Discuss National Support Framework

6/1/2011 - 12/1/2011

Setup Online Forums

7/1/2011 - 10/1/2011

Optional Considerations

Smartphone for Cathy?

1/1/2011 - 5/1/2011

Upgrade to Ethernet?

4/1/2011 - 10/1/2011

Setup Wiki Solution?

7/1/2011 - 10/1/2011