CSP Grant Due

08/30/2013

Edtec?
i3

Website Up

09/01/2013

Community Outreach Begins

09/03/2013

Staff Recruitment Begins

10/01/2013

Walton Grant

10/01/2013

This dates is not in stone. I am hearing that Walton is thinking of providing more money to full transformation schools.

Student/School Culture Plan

11/01/2013

Curriculum (scope and sequence, curriculum maps, etc.) developed

12/31/2013

Director of Operations Hired

01/15/2014

2014/15 Final Budget

02/28/2014

so that we can be comfortable with offers for April.

Afterschool partnership or plan

03/01/2014

100% of teachers hired

04/01/2014

Audit Provider Identified

04/01/2014

100% of budgeted students enrolled

04/30/2014

100% of school staff (non teaching) hired

05/30/2014

IT and Interface with all applicable systems – EdTec, State, ASD

06/05/2014

Facility ready for students

07/01/2014