SBBB

Main

initiation

09/23/2010

preliminary agreement for design works

02/09/2011

team and process specified

müellif muvakkatnamesi

02/11/2011

may not be necessary

team set

02/17/2011

statical
preservation
application dwg
control works
siteworks

brief and design scheme approval

02/28/2011

Preliminary design project approval (client)

03/11/2011

application to preservation committee

03/11/2011

preservation cmmtt approval

04/29/2011

application to Bogaziçi İmar

05/02/2011

Bogaiçi İmar approval

05/31/2011

Fire Up @ site

06/30/2011

meeting

can Arık meeting

10/14/2010

project MTG

10/30/2010

phone call NEFTÇI

01/19/2011

we talked twice

meet NİŞLİ ANITLAR

01/20/2011

meet Atilla Atalay

02/01/2011

meet Mehmet Alper TURES

02/03/2011

site visit

01 explore

10/16/2010

visit to timber workshops

10/16/2010

02 inventory

02/11/2011

zemin etüdü ve kot gabari alınması

02/14/2011 - 02/28/2011

task

research and design

02/07/2011 - 02/28/2011

preliminary design project

02/07/2011 - 02/28/2011

avant project for Bogaiçi İmar

03/01/2011 - 03/31/2011

application drawings

05/02/2011 - 05/31/2011

construction

07/01/2011 - 11/01/2011

yazışma