131018 BPP Web App Timeline

SIMULATION (JUNE 25-SEPT 16)

Anchor Screens UI (NH)

06/25/2013 - 07/19/2013

Rest of Screens UI (NH)

07/19/2013 - 08/03/2013

Proto.io (EJ)

08/3/2013 - 08/12/2013

Focus Group 1st Round (AC)

08/12/2013 - 8/16/2013

Screens 2nd Round (NH)

08/16/2013 - 08/29/2013

Proto.io 2nd Round (EJ)

08/29/2013 - 09/03/2013

UI Design Review (TP)

09/03/2013 - 09/06/2013

Screens Final Designs (NH)

09/06/2013 - 09/11/2013

Proto.io Final (EJ)

09/11/2013 - 09/16/2013

SIMULATION & "WIREFRAME" COMPLETE (SEPT 16)

09/16/2013

DEVELOPMENT (SEPT 16-NOV 1)

Hire Programmers (AC)

09/16/2013 - 09/30/2013

App Spec Development (Weekly SCRUM)

09/30/2013 - 10/21/2013

Backend Server & Web Admin Development

09/30/2013 - 10/31/2013

App Development (Weekly SCRUM)

10/21/2013 - 10/31/2013

BPP WEB APP 1.0 FIELD TRIAL READY (NOV 1)

11/01/2013

FIELD TRIAL (NOV 1-DEC 13)

Sign Up CU Sponsors and Recruit 300 Participants

10/1/2013 - 10/31/2013

Field Trial at CU-Boulder

11/1/2013 - 12/13/2013

"Train the Trainers"

11/4/2013 - 11/05/2013

Formal feedback - Phase I

11/20/2013 - 11/22/2013

Fall Break (no school)

11/25/2013 - 11/29/2013

Field Trial - Update Release Phase 2

12/2/2013 - 12/3/2013

Formal feedback - Phase 2

12/12/2013 - 12/13/2013

FIELD TRIAL ENDS (DEC 13)

12/13/2013