DoS Proposal Timeline

Events

Project Begins

10/01/2013

SU Delegation to Pyongyang

03/09/2014 - 03/14/2014

Needs assessment, summer program planning, DPRK
participant screening

First Summer Program (Dalian, PRC)

06/01/2014 - 06/21/2014

English Science Village 1

Initiate Licensing Request

07/01/2014

SU Delegation to Pyongyang

03/08/2015 - 03/13/2015

Establish Science Village at SAOS (bring, install equipment); Conduct post-program tests

Second Summer Program (Dalian, PRC)

06/01/2015 - 06/21/2015

English Science Village 2

SU Delegation to Pyongyang

08/01/2015 - 08/06/2015

Refine Science Village; conduct on-site evaluations

Prepare Final Report

09/01/2015 - 09/30/2015

Assessments

Pre-program Assessment

06/01/2014

Post-program Assessment

06/21/2014

Mid-program Evaluation

03/10/2015

Pre-program Assessment

06/01/2015

Post-program Assessment

06/21/2015