Contact Inquiry to Veiltech

11/02/2012 - 11/05/2012

Inquired about building app for CAT

Login to AL provided

11/12/2012 - 11/13/2012

Login Provided to AL 11/12, 11/13 return email and response promised by end of day by Cosman.

Go ahead by CAT

11/17/2012 - 11/29/2012

11/17 Emails from Curt/Matt to Cosman. No response from cosman until 11/29 as it "got lost in email"

GoToMeeting on Scope

12/03/2012 - 12/04/2012

Call Change die to CAT Roofing Issue

12/04/2012 - 12/05/2012

Received QB proposal

12/14/2012 - 12/15/2012

received QB proposal.
Application Overhaul 4 Weeks
Dashboard 6 Weeks
Google Maps Integration 8 Weeks
Drive 12 Weeks
Trackers 10 Weeks

KICK OFF MEETING

12/21/2012 - 12/22/2012

Kick Off Meeting to discuss beginning project, Curt Drove from ST Louis, Pulled workers from desks as this was "to be a big meeting" lasted briefly not much accomplished

Update for XML Drop In & Paid again

12/28/2012 - 12/29/2012

Made addition for xml drop in on Eagleview

Timeframe Application Overhaul

01/07/2013 - 02/04/2013

Timeframe given for App Overhaul.

Timeframe Dashboard

01/07/2013 - 02/18/2013

Timeframe to complete custom dashboard

Timeframe for Drive Intgegration

01/07/2013 - 04/01/2013

Timeframe to get Google Drive Integration done

Timeframe for Google Maps Integration

01/07/2013 - 03/04/2013

Time Frame for Google Maps Integration

Trackers Time Frame

01/07/2013 - 03/18/2013

Time to Build Tracking Systems

First request to look at picto for XML drop in

01/24/2013 - 01/25/2013