Cooperative Endeavor Agreement signed by Mr. Spinosa & Mayor Holden 09/26/10

09/26/10

Cooperative Endeavor Agreement recorded with Clerk of Court. 09/27/10

09/27/10

Concept Design Presentation to the Library Board of Control. 12/16/2010

12/16/10

Design Development. Building Review of the Rouzan Branch Library. 2011-2012

01/01/2011 - 12/31/2012

Meeting To Discuss Responsibilities During Construction of the Library. 06/01/12

06/01/12

Meeting with Mr. Tommy Spinosa, Jr., Mr. Leo D'Aubin, Parish Attorney, Mr. Stanford O. Bardwell, Jr., Ms. Patricia Husband and Ms. Mary Stein, Assistant Library Directors.

July,September,October 2012. Ongoing Revisions to Cooperative Endeavor Agreement

07/01/2012 - 10/31/2012

Library Board of Control Discusses Updates to Cooperative Endeavor Agreement.

11/15/12

Includes a Deadline of February 15th, 2013 for the Infrastructure to be Completed or Bonded.

2590 Receives Notice to Proceed on Infrastructure. 02/19/13

02/19/2013

Entergy Scheduled to Disconnect Gas at Demolished House on Property. 04/24/13

04/24/13

Estimated Date to Complete Infrastructure. 11/15/13

11/15/13

DPW Can Begin Public Bid Process to Select Library's General Contractor. 11/2013

11/16/2013

Permits and Groundbreaking. 11/13

11/16/13 - 11/30/13

Estimated 18 Months to Complete

11/16/13 - 05/16/15