Construction Timeline

Pre-Design Meetings Summer 2012

08/15/2012

Interviewed Stakeholders Fall 2012

10/15/2012

Submit Programming. DPW/User Agency Comments and Approval February 22

02/15/2013 - 02/22/2013

Building Program Delivered. March 15, 2013

03/15/2013

Schematic Design Phase. April, 2013

04/01/2013 - 04/30/2013

Submit Schematic Design. DPW/User Agency Comments and Approval May 20

05/06/2013 - 05/20/2013

Design Development Continues

05/21/2013 - 08/18/2013

Submit Design Development. DPW/User Agency Comments and Approval September 2

08/19/2013 - 09/02/2013

Submit Construction Documents. DPW/User Agency Comments and Approval March 17

03/03/2014 - 03/17/2014

Bids Submitted

04/18/2014

Select Contractor Through Public Bid in 2014

04/19/2014

Construction of New Building (estimated)

04/20/2014 - 04/20/2016

Construction Closeout (estimated)

04/19/2016