June 1, 2020 - July 31, 2021
% complete
This phase will run from Summer 2020 to Summer 2021
July 14, 2021 - September 1, 2022
% complete
This Phase will take place between Summer 2021 and Spring 2022
https://nm14cerrillos.nmdotprojects.org/#resources
July 21, 2021
% complete
April 26, 2022
% complete
August 1, 2022 - January 1, 2023
% complete
Conduct Environmental Surveys and Analyze Effects
Conduct Agency Consultation
Obtain Authorization to Design and Construct Improvements
September 1, 2022
% complete
September 1, 2022 - November 30, 2024
% complete
December 1, 2023 - February 29, 2024
% complete
A Phase C Public Meeting should take place in the Spring/Summer of 2023. Specific dates to be determined.
March 15, 2025
% complete
Phase 2 and Phase 3 Construction TBD (pending funding)