EDER 679: Final Project

Professional Development Modules for Teacher Technology Training

Main

Planning and Definition

Module Development Plan

09/01/2010 - 09/03/2010

Meet to decide on modules to be developed, order and mode of delivery. Project vision and scope document.

Project Plan

09/03/10 12:00:00 AM - 09/10/2010

Project Plan Finalization

AISI Application

09/10/10 12:00:00 AM - 09/14/2010

Application is developed and submitted to administration.

Project Team Assignment

09/14/10 12:00:00 AM - 09/17/2010

Project work team identified and assigned.

Project Charter and SOW

09/17/10 12:00:00 AM - 09/21/2010

Project charter & Statement of Work signed off by Project manager and project Sponsor.

Communication Plan

09/21/10 12:00:00 AM - 09/23/2010

Communication Plan signed off between Project Manager and Project Sponsor

Analysis, Design & Development

Learner Analysis: Conduct Survey

09/24/10 12:00:00 AM - 10/01/2010

Conduct e-mail survey

Learner Analysis: Build Survey

09/24/2010

Build survey to determine interest, comfort level and experience with Educational Technology

Learner Analysis: Analyze Responses

10/01/10 12:00:00 AM - 10/06/2010

Analyze responses to determine learner needs.

Module Design

10/06/10 12:00:00 AM - 10/13/2010

Determine concept design for module delivery to maintain uniformity.

Content Development: Module One

10/13/10 12:00:00 AM - 10/26/2010

Content Development: Module 1

Content Development: Module Two

10/26/10 12:00:00 AM - 11/08/2010

Develop Module 2

Content Development: Module Three

11/08/10 12:00:00 AM - 11/22/2010

Develop Module 3

Content Development: Module Four

11/22/10 12:00:00 AM - 12/03/2010

Develop Module 4

Content Development: Module Two Evaluation

11/25/2010 - 11/28/2010

Make necessary changes to module 2 based on module 1 evaluation.

Content Development: Module Five

12/03/10 12:00:00 AM - 12/16/2010

Develop Module 5

Content Development: Module Three Evaluation

01/12/2011 - 01/13/2011

Make necessary changes to module 3 based on module 2 evaluation.

Content Development: Module Four Evaluation

02/16/2011 - 02/17/2011

Make necessary changes to module 4 based on module 3 evaluation.

Content Development: Module Five Evaluation

03/16/2011 - 03/17/2011

Make necessary changes to module 5 based on module 4 evaluation.

Delivery

Module One: Sign Up

09/27/2010 - 11/05/2010

Workshop #1 – online sign up

Module One: Prep Requirements

11/05/10 12:00:00 AM - 11/08/2010

Assign Preparation requirements

Module One: Run Workshop

11/08/10 12:00:00 AM - 11/16/2010

Run Workshop

Module One: Evaluations

11/16/10 12:00:00 AM - 11/17/2010

Send workshop evaluations via e-mail

Module Two: Sign Up

11/17/10 12:00:00 AM - 12/10/2010

Workshop #2 Online Sign up

Module Two: Prep Requirements

12/10/10 12:00:00 AM - 12/13/2010

Assign Preparation requirements

Module Two: Run Workshop

12/13/10 12:00:00 AM - 01/04/2011

Run Workshop

Module Two: Evaluations

01/04/11 12:00:00 AM - 01/05/2011

Send workshop evaluations via e-mail

Module Three: Sign Up

01/05/11 12:00:00 AM - 01/28/2011

Workshop #3 online sign up

Module Three: Prep Requirements

01/28/11 12:00:00 AM - 01/31/2011

Assign Preparation requirements

Module Three: Run Workshop

01/31/11 12:00:00 AM - 02/08/2011

Run Workshop

Module Three: Evaluation

02/08/11 12:00:00 AM - 02/09/2011

Send workshop evaluations via e-mail

Module Four: Sign Up

02/09/11 12:00:00 AM - 02/25/2011

Workshop #4 online sign up

Module Four: Prep Requirements

02/25/11 12:00:00 AM - 02/28/2011

Assign Preparation requirements

Module Four: Run Workshop

02/28/11 12:00:00 AM - 03/08/2011

Run Workshop

Module Four: Evaluations

03/08/11 12:00:00 AM - 03/09/2011

Send workshop evaluations via e-mail

Module Five: Sign Up

03/09/11 12:00:00 AM - 04/01/2011

Workshop #5 online sign up

Module Five: Prep Requirements

04/01/11 12:00:00 AM - 04/04/2011

Assign Preparation requirements

Module Five: Run Workshop

04/04/11 12:00:00 AM - 04/12/2011

Run Workshop

Module Five: Evaluation

04/12/11 12:00:00 AM - 04/13/2011

Send workshop evaluations via e-mail

Project Close

Project Evaluation

04/20/2011 - 04/25/2011

Meet with Project team to determine best/worst practices. Summarize workshop evaluations for modules 1 through 5.

Project Closure Report

04/25/11 12:00:00 AM - 04/28/2011

Complete report and necessary documentation and submit

Project Close

04/28/11 12:00:00 AM

Close project with project sponsor