Integrative Services at Amplatz

Main

Planning for Program Development

05/01/2013 - 05/31/2013

This phase is for prioritizing next steps, securing funding, and recruiting a clinical lead. Aligns with sections of recommendation ten.

Development of Framework for Integrative Services Program

06/01/2013 - 08/30/2013

Clinical lead will use recommendations document as a guideline to develop the education and implementation framework. Along side this framework a plan for evaluation should be developed. Upgrade of the Epic system may be required at this time depending on the evaluation metrics developed. Comprehensive policies and procedures should be put into place during this time. Aligns with sections of recommendations eight, ten and planning for three and seven.

Launch Staff Education

09/01/2013 - 11/30/2013

Aligns with recommendation seven.

Develop Parent Support Services

10/01/2013 - 03/31/2014

While this process will be ongoing and revised often, this step represents the initial revamping of parent support services as outlined in recommendation five.

Expand Patient and Family Education

10/01/2013 - 03/31/2014

Aligns with recommendation six.

Establish an Integrative Therapies Research Program

01/01/2014 - 03/31/2014

Aligns with recommendation nine.

Create and Integrative Health Consult Service

04/01/2014 - 10/31/2014

Aligns with recommendation four.