NROR Timeline

Organizational Milestones

NROR organizational structure formed

11/01/2010

ITIC committee formed and EMR vendors engaged

02/01/2011

Stakeholder forum held in Washington, D.C.

04/01/2012

System Design & Development

Initial data dictionary, user requirements and system architecture developed

02/01/2011 - 07/31/2011

RFP and vendor selection

08/01/2011 - 03/01/2012

System Development

04/01/2012 - 06/30/2013

System Beta Testing

12/01/2012 - 06/30/2013

Version 2 of Data Dictionary released

2/1/2013

Begin development of data dictionary/metrics for next disease site (anticipated)

7/1/2014

Add patient reported outcomes (anticipated)

7/1/2014

Pilot Protocol Development

Pilot site selection process

06/01/2012 - 04/01/2013

Central IRB selection and protocol approval

09/01/2012 - 12/31/2012

Initial set of radiation practice metrics developed and approved

09/01/2012 - 11/01/2012

Registry Active

Prostate Pilot Launch (anticipated)

07/01/2013

Expansion of prostate pilot nationally (anticipated)

7/1/2014

Expansion to other disease sites (anticipated)

7/1/2015