SU and Upgrade Timeline

SU Installs and Upgrades

Install MU Wave 1 & 2 SUs

5/6/13 - 5/17/13

Install MU Wave 3 SUs

7/1/13 - 7/19/13

Upgrade to 2012 IU5

7/1/13 - 7/19/13

Install all available SUs

8/12/13 - 8/30/13

Timeframe is shorter than other SU loads because there will be less testing.

Install all available SUs

10/7/13 - 11/15/13

Install all available SUs

1/16/14 - 3/7/14

Final package before Go Live. All other SUs will have to be ad hoc.

Install all available SUs

5/1/14 - 6/27/14

8-week process that repeats indefinitely.

Install all available SUs

7/1/14 - 8/29/14

Last major SU load while on 2012.

Upgrade to 2014 IU1

7/1/14 - 12/14/14

Milestones

Integrated Testing begins

9/2/13

PRD install trip

1/6/14

Go Live

4/1/14

ICD-10

10/1/14

PRD upgrade complete

12/14/14