EXTENDED PROJECT

Other commitments

Easter Holiday

03/29/2013 - 04/12/2013

I'll be revising for my exams in May/June so will have limited time to spend on my EP

D of E Yorks

05/03/2013 - 05/06/2013

Study Leave

05/10/2013 - 06/10/2013

Biology Exam

05/16/2013

Biology Exam

05/21/2013

Geography exam

05/21/2013

Geology Exam

05/22/2013

Chemistry Exam

05/23/2013

Biology Exam

06/03/2013

Chemistry Exam

06/04/2013

Camping (Beach)

06/05/2013 - 06/07/2013

Hand in option one

07/09/2013

D OF E LAKES

07/09/2013 - 07/12/2013

SUMMER HOLIDAYS

07/17/2013 - 08/28/2013

D of E Wales

08/18/2013 - 08/23/2013

FINAL HAND IN DATE

10/09/2013

DEADLINES

complete rationale and start research

06/16/2013

Start designing (initial sketches etc.)

08/01/2013

Finish all designs and order the wood

08/18/2013

Have all the materials

08/20/2013

Final checks to make sure i have all the materials I need. Get anything which I haven't recieved yet

Start building

08/25/2013

All materials should be available so that everythign is onhand to start building the house

Complete midterm review

08/31/2013

Completely finished chicken house

09/30/2013

The house must be completely finished by now so there is time to evaluate

Complete all written work- apart from evaluation

10/08/2013

HAND IN DATE

10/10/2013