Again, attempting to compress the hardening due to higher trust in automation and leveraging Flyway implementation.
Again, attempting to compress the hardening due to higher trust in automation and leveraging Flyway implementation.
November 11, 2019 - November 20, 2019
% complete
COPS team to finish deployment script of EC Smart to AWS
November 22, 2019
% complete
No more planned changes to be made to the product. Only new bugfixes and security fixes are allowed, as part of hardening.
RC0 Tag: First test cycle env.
November 22, 2019
% complete
No more planned changes to be made to the product. Only critical/blocker bug fixes and security fixes are allowed, as part of hardening.
Any changes needed for the release is made in DEFAULT, and only merged to RELEASE branch upon GREEN build.
November 25, 2019 - December 5, 2019
% complete
Connect with 2-3 customer projects with EC-12.2 and EC Smart prospects that can be used to test installation of 12.2 upgrade script.
Ownership to be placed with COPS team.
November 25, 2019 - December 12, 2019
% complete
November 25, 2019 - November 25, 2019
% complete
November 25, 2019 - November 25, 2019
% complete
Testing migrating from EC 12.2 pure environment to the EC Smart based one.
November 26, 2019 - November 29, 2019
% complete
Manual testing:
- Execution of all the ECPTs related to the planned scope
- Critical regression tests (not yet automated)
Automated Tests (ALL)
November 26, 2019 - December 2, 2019
% complete
Fixing bugs found during TC1, or critical/blocker bugs accepted passed the Scope Work Done point.
December 2, 2019
% complete
Allow for team to incorporate the class changes into the migration script that will be used for TC2
December 2, 2019
% complete
December 3, 2019 - December 3, 2019
% complete
Ready by morning CET next day.
December 3, 2019 - December 3, 2019
% complete
December 4, 2019 - 1 day
% complete
Exploratory testing, for all PRD and PRS who can participate.
Upgraded 12.2.RC0 environment.
December 4, 2019 - December 6, 2019
% complete
Manual testing:
- ALL not-yet-automated Regression Tests
- Failed and Fixed issues in TC1
- Test blocked/NA/not completed in TC1
- (N/A) Retest scope issues having db upgrade impact area info in JIRA
- Exploratory Testing of key functional areas
Automated testing (ALL):
- Functional UI regression/scenarios tests
- Functional Issue tests
- Screen/Smoke tests (IUD)
- Performance tests
- Security (Veracode Scan)
- Scenario Tester (Revenue)
- Run automated regression tests on Imported DB
Scope:
- Testing on Upgrade environment
- Manual Test Execution on Upgrade and Plain Environment
December 4, 2019 - December 9, 2019
% complete
Fixing bugs found in TC2
December 9, 2019 - January 6, 2020
% complete
Final review and generation of PDFs
December 10, 2019 - December 10, 2019
% complete
Ready by morning CET next day.
December 11, 2019 - December 30, 2019
% complete
Manual testing:
- ALL not-yet-automated Regression Tests
- Failed and Fixed issues in TC1
- Test blocked/NA/not completed in TC1
- (N/A) Retest scope issues having db upgrade impact area info in JIRA
- Exploratory Testing of key functional areas
Automated testing (ALL):
- Functional UI regression/scenarios tests
- Functional Issue tests
- Screen/Smoke tests (IUD)
- Performance tests
- Security (Veracode Scan)
- Scenario Tester (Revenue)
- Run automated regression tests on Imported DB
Scope:
- Testing on Upgrade environment
- Manual Test Execution on Upgrade and Plain Environment
December 11, 2019 - January 1, 2020
% complete
Fixing bugs found in TC2
December 13, 2019 - December 13, 2019
% complete
January 1, 2020
% complete
January 2, 2020 - January 2, 2020
% complete
January 3, 2020 - 4 days
% complete
Last test cycle, based on final RC, validating blocker fixes from TC2.
January 3, 2020 - 4 days
% complete
Exploratory Testing of Critical Path scenarios, sign-off that all key features work as expected.
January 7, 2020
% complete
January 8, 2020
% complete
Our goal is to release as short as possible after the GO/NO-GO decision.
November 18, 2019 - December 5, 2019
% complete
Release Details document: http://ecpedia.eu.tieto.com/display/RD122/EC-12.2+-+JIRA+Filters+for+Release+Details
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE122/EC-12.2+Documentation+Scope
November 19, 2019 - December 2, 2019
% complete
Highlights document (in the Release Notes):
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Notes#EC-12.1-SP01-ReleaseNotes-Highlights
Content refinement from Release Scope page:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Release+Scope
Responsibility: Release Team
December 2, 2019 - December 5, 2019
% complete
Installation Guide document:
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1+-+Installation+Guide
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
December 4, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Offline Help to be generated in Bug Quest 1 or TC1 env (EC screen).
All product teams need to verify the Offline Help (BF documents) throughout TC1 and TC2.
December 5, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Offline Help to be generated in Bug Quest 2 or TC2 env (EC screen).
Fixes of Offline Help in TC1 will be available in TC2 Offline Help.
All product teams need to verify the Offline Help (BF documents) throughout TC1 and TC2.
December 6, 2019
% complete
Preparation, modifications and verification by POs & PMs.
Technical Overview document:
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1+-+Technical+Overview
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
December 6, 2019
% complete
Preparation and verification by POs & PMs.
Known Limitations (in the Release Notes):
http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Notes#EC-12.1-SP01-ReleaseNotes-KnownLimitations
December 6, 2019 - December 6, 2019
% complete
Responsibility: POs and Release Team (final verification)
Release Details document: http://ecpedia.eu.tieto.com/display/RD121/EC-12.1-SP01+-+Release+Details
Documentation Scope:
http://ecpedia.eu.tieto.com/display/RE121/EC-12.1-SP01+Documentation+Scope
December 9, 2019
% complete
Test Online Help installation by Release Team (2nd trial)
December 18, 2019
% complete
Responsibility: Release Team to generate the Offline Help:
- PDFs BF Documents
- HTML version
Teams need to review again the affected Offline Help (which was fixed in TC2)
Release Team briefly review the final Offline Help before upload to ECUC.