Detector Sensitivity Analysis

Overall

Contract

5/1/10 - 11/20/10

Preliminary Design Analysis

5/14/10 - 6/3/10

Design preamp circuits, find pickoff points
Design chopper wheels
Design test rig, etc

Procurement Lead Time

5/28/10 - 6/17/10

GR

PbS, Lock=Yes?, ~1200 Hz

Instrument Head

6/17/2010 - 6/23/2010

Verify Test Setup

6/24/10 - 6/28/10

Verify Focus
Verify BB calibration

Conduct Testing

6/29/10 - 7/5/10

Post Process Data

7/6/10 - 7/12/10

Implement and Model

7/13/10 - 7/26/10

AL

InSb, Lock=N, 1200 Hz

Instrument Head

6/24/10 - 6/30/10

Verify Test Setup

7/1/10 - 7/5/10

Conduct Testing

7/6/10 - 7/12/10

Post Process Data

7/13/10 - 7/19/10

Implement and Model

7/28/10 - 8/17/10

AS

InSb, Lock=No, 1200 Hz

Instrument Head

7/1/10 - 7/7/10

Verify Test Setup

7/13/10

Conduct Testing

7/14/10 - 7/20/10

Post Process Data

7/21/10 - 7/27/10

Implement and Model

7/28/10 - 8/17/10

AF

PbS, InSb, Lock=Y, 100 Hz

Instrument Head

7/8/10 - 7/21/10

Verify Test Setup

7/21/10 - 7/26/10

Conduct Testing

7/27/10 - 8/9/10

Post Process Data

8/10/10 - 8/23/10

Implement and Model

8/24/10 - 9/6/10

RS

InSb, Contrast PbS, 400-1200 Hz

Instrument Head

7/22/10 - 8/4/10

Verify Test Setup

8/10/10 - 8/13/10

Conduct Testing

8/16/10 - 8/27/10

Post Process Data

8/30/10 - 9/10/10

Implement and Model

9/13/10 - 9/24/10