26 February 2020
% complete
Official project kick-off! (2020)
New requirements presented along with functional and design elements.
27 February 2020 - 8 March 2020
% complete
Discovery phase based on newly provided requirements in order to find the best solution and identify any potential issues and/or limitations.
9 March 2020
% complete
Acceptance of proposed solution and any limitations that it may imply based on the latest requirements.
9 March 2020 - 1 week
% complete
Banner/Homepage take over/Micros-site designs based on latest requirements. Including existing and new elements that were agreed upon.
16 March 2020
% complete
CAE to be presented and approve the delivered designs for the banner/homepage takeover/Micro-site and included elements based on latest requirements.
16 March 2020 - 1 week
% complete
Frontend development of the site based on the approved designs. This includes all HTML/CCS and interactions.
16 March 2020 - 2 weeks
% complete
Creation of all CMS templates and elements. Includes all functionality, frontend and backend, as required by the approved solution. *also includes the setup and configuration of the required micro-site.
30 March 2020
% complete
Deadline to submit all content English and French , including images, downloads and any other related assets that need to be available for the "launch" of the Darksite
30 March 2020 - 3 days
% complete
Integration of all content as provided and required for launch of the site. This includes all assets, images, and documents.
2 April 2020 - 4 days
% complete
CAE to QA the complete solution and give their final approval. SW to implement the changes/updates as presented.
6 April 2020 - 3 days
% complete
Preparation of the solution for go-live.
9 April 2020
% complete
The Darksite features are now available to use in production