Water Cannon Delivery Time Line

Design

Design Process

03/01/2013 - 03/22/2013

21 days

Darley

Engine Driven Pump Delivery

03/01/2013 - 06/11/2013

90 days for Pump to be built.
Shipped by Air - + 10 days. 3 months 10 days

Pump Installation

06/11/2013 - 06/25/2013

14 days

AKRON

Monitors Delivery

03/01/2013 - 04/07/2013

4 to 6 weeks delivery time

Monitors Installation

04/23/2013 - 05/07/2013

Needs to be done after piping is finished. 14 days

TANKS

GRP Tanks

03/23/2013 - 04/23/2013

7000 + 200 L ( After Talking with foreman in GRP section). 1 month

SS Tanks

03/23/2013 - 03/27/2013

100 + 100 L Tanks (After Talking with Foreman in the SS Section). 4 days

Electricals

Electricals

03/23/2013 - 04/13/2013

For Monitors and other items. 21 days

Piping

Piping Installation

03/23/2013 - 04/22/2013

Assuming Piping installation can go ahead before arrival of pump. 30 days