NNAHS - Lakeside (Floor 11, Roof 4, Roof 11)

Eleventh Floor

ACT Sampling Starts (81)

06/15/2012 - 06/16/2012

Analysis of All Sample(s) Complete (82)

06/18/2012 - 06/19/2012

ACT Releases Floor for Work (83)

06/18/2012 - 06/19/2012

Written Results Rcvd by JED (84)

06/19/2012 - 06/20/2012

MBA Demo Starts (87)

06/22/2012 - 06/23/2012

Floor Diagram Rcvd by JED (85)

07/06/2012 - 07/07/2012

Written Results to MBA (86)

07/10/2012 - 07/11/2012

AD Abatement Starts -->> 10/15/12 (88)

09/24/2012 - 09/25/2012

Roof (4th Floor)

ACT Sampling Starts (89)

07/31/2012 - 08/01/2012

Analysis of All Sample(s) Complete (90)

08/09/2012 - 08/10/2012

ACT Gives Notice No ACM Detected (91)

08/09/2012 - 08/10/2012

Written Results Rcvd by JED (92)

08/20/2012 - 08/21/2012

[To Date: No Work Performed on Roof]

09/03/2012 - 09/04/2012

Roof (11th Floor)

ACT Sampling Starts (93)

06/15/2012 - 06/16/2012

Analysis of All Sample(s) Complete (94)

06/18/2012 - 06/19/2012

ACT Releases Roof for Work (95)

06/18/2012 - 06/19/2012

Written Results Rcvd by JED (96)

06/19/2012 - 06/20/2012

AD Abatement Starts -->> 12/13/12 (97)

09/24/2012 - 09/25/2012