NNAHS, Lakeside - Asbestos Activity (Flrs 7-9)

Seventh Floor

ACT Sampling Starts (49)

06/12/2012 - 06/13/2012

ACT Releases Floor for Work (51)

06/13/2012 - 06/14/2012

Analysis of All Sample(s) Complete (50)

06/13/2012 - 06/14/2012

Written Results Rcvd by JED (52)

06/19/2012 - 06/20/2012

Floor Diagram Rcvd by JED (53)

06/22/2012 - 06/23/2012

AD Abatement Starts (56)

06/27/2012 - 06/28/2012

MBA Demo Starts (55)

06/28/2012 - 06/29/2012

Written Results to MBA (54)

07/01/2012 - 07/02/2012

Eighth Floor

ACT Sampling Starts (57)

06/06/2012 - 06/07/2012

Analysis of All Sample(s) Complete (58)

06/09/2012 - 06/10/2012

ACT Releases Floor for Work (59)

06/09/2012 - 06/10/2012

Written Results Rcvd by JED (60)

06/11/2012 - 06/12/2012

Floor Diagram Rcvd by JED (61)

06/22/2012 - 06/23/2012

AD Abatement Starts (64)

06/25/2012 - 06/26/2012

MBA Demo Starts (63)

06/26/2012 - 06/27/2012

Written Results to MBA (62)

07/01/2012 - 07/02/2012

Ninth Floor

ACT Sampling Starts (65)

06/06/2012 - 06/07/2012

ACT Releases Floor for Work (67)

06/07/2012 - 06/08/2012

Analysis of All Sample(s) Complete (66)

06/07/2012 - 06/08/2012

Written Results Rcvd by JED (68)

06/11/2012 - 06/12/2012

Floor Diagram Rcvd by JED (69)

06/22/2012 - 06/23/2012

AD Abatement Starts (72)

06/25/2012 - 06/26/2012

Written Results to MBA (70)

06/29/2012 - 06/30/2012

MBA Demos Starts (71)

07/02/2012 - 07/03/2012

Tenth Floor

ACT Sampling Starts (73)

05/30/2012 - 05/31/2012

ACT Releases Floor for Work (75)

05/31/2012 - 06/01/2012

Analysis of All Sample(s) Complete (74)

05/31/2012 - 06/01/2012

Written Results Rcvd by JED (76)

06/10/2012 - 06/11/2012

Floor Diagram Rcvd by JED (77)

06/20/2012 - 06/21/2012

AD Abatement Starts (80)

06/22/2012 - 06/23/2012

MBA Demo Starts (79)

06/22/2012 - 06/23/2012

Written Results to MBA (78)

07/01/2012 - 07/02/2012