NNAHS- Lakeside - Asbestos Activity (Flrs 4-6)

Fourth Floor

ACT Sampling Starts (25)

06/14/2012 - 06/15/2012

ACT Releases Floor for Work (27)

06/15/2012 - 06/16/2012

Analysis of All Sample(s) Complete (26)

06/15/2012 - 06/16/2012

Written Results Rcvd by JED (28)

06/18/2012 - 06/19/2012

Floor Diagram Rcvd by JED (29)

07/03/2012 - 07/04/2012

Written Results to MBA (31)

07/10/2012 - 07/11/2012

MBA Demo Starts (30)

07/24/2012 - 07/25/2012

AD Abatement Starts (32)

08/07/2012 - 08/08/2012

Fifth Floor

ACT Sampling Starts (33)

06/13/2012 - 06/14/2012

ACT Releases Floor for Work (35)

06/15/2012 - 06/16/2012

Analysis of All Sample(s) Complete (34)

06/15/2012 - 06/16/2012

Written Results Rcvd by JED (36)

06/18/2012 - 06/19/2012

MBA Demo Starts (39)

06/29/2012 - 06/30/2012

AD Abatement Starts (40)

06/29/2012 - 06/30/2012

Floor Diagram Rcvd by JED (37)

07/03/2012 - 07/04/2012

Written Results to MBA (38)

07/10/2012 - 07/11/2012

Sixth Floor

ACT Sampling Starts (41)

06/13/2012 - 06/14/2012

ACT Releases Floor for Work (43)

06/14/2012 - 06/15/2012

Analysis of All Sample(s) Complete (42)

06/14/2012 - 06/15/2012

Written Results Rcvd by JED (44)

06/19/2012 - 06/20/2012

MBA Demo Starts (47)

06/29/2012 - 06/30/2012

AD Abatement Starts (48)

06/29/2012 - 06/30/2012

Floor Diagram Rcvd by JED (45)

07/03/2012 - 07/04/2012

Written Results to MBA (46)

07/10/2012 - 07/11/2012