First Floor

ACT Sampling Starts (1)

06/26/2012 - 06/27/2012

ACT Releases Floor for Work (3)

06/28/2012 - 06/29/2012

Analysis of All Sample(s) Complete (2)

06/28/2012 - 06/29/2012

MBA Demo Starts (4)

07/09/2012 - 07/10/2012

Floor Diagram Rcvd by JED (6)

07/10/2012 - 07/11/2012

Written Results Rcvd by JED (5)

07/10/2012 - 07/11/2012

Written Results to MBA (7)

07/11/2012 - 07/12/2012

AD Abatement Starts (8)

07/23/2012 - 07/24/2012

Second Floor

ACT Sampling Starts (9)

06/26/2012 - 06/27/2012

Analysis of All Sample(s) Complete (11)

06/27/2012 - 06/28/2012

ACT Release Floor for Work (10)

06/27/2012 - 06/28/2012

Written Results Rcvd by JED (12)

07/10/2012 - 07/11/2012

Floor Diagram Rcvd by JED (13)

07/10/2012 - 07/11/2012

Written Results to MBA (14)

07/11/2012 - 07/12/2012

MBA Demo Starts (15)

07/16/2012 - 07/17/2012

AD Abatement Starts (16)

07/26/2012 - 07/27/2012

Third Floor

ACT Sampling Starts (17)

06/27/2012 - 06/28/2012

Analysis of All Sample(s) Complete (18)

06/28/2012 - 06/29/2012

Act Releases Floor for Work (19)

06/28/2012 - 06/29/2012

Floor Diagram Rcvd by JED (20)

07/10/2012 - 07/11/2012

from ACT

Written Results to MBA (22)

07/10/2012 - 07/11/2012

Written Results Rcvd by JED (21)

07/10/2012 - 07/11/2012

MBA Demo Starts (23)

07/19/2012 - 07/20/2012

AD Abatement Starts (24)

07/31/2012 - 08/01/2012