Cummins Rocky Mountain, LLC - BI Roadmap

High level project timeline for implmenting OBIEE

BI Program Roadmap

Overall Roadmap

Deploy NPS/Shoretel/Customer Sales prototypes into production

4/19/2010 - 5/31/2010

Phase 1 - Finance (GL,Profitability) and Service (Productivity, RECT)

05/31/2010 - 9/5/2010

Project with eVerge Consulting

Merge Custom Dashboard into Phase 1 Project

8/1/2010 - 9/16/2010

Take current dashbaords for Daily Sales / NPS / Shoretel / Customer Sales and bolt them into the main eVerge project data warehouse.

Phase 2 Project

9/16/2010 - 12/16/2010

Phase 1 OBIEE Project Breakdown

Infrastructure setup

5/31/2010 - 6/14/2010

OBIEE, Informatica, DAC

Custom Star Design

6/14/2010 - 6/28/2010

Productivity and RECT

Initial Data Loads / Prototype #1

6/28/2010 - 7/12/2010

OBIEE Development / Prototype #2

7/12/2010 - 7/26/2010

Dashboard Development / Final prototype

7/26/2010 - 8/09/2010

Code Finalization & Testing

8/9/2010 - 8/16/2010

User Acceptance Testing (UAT)

8/16/2010 - 8/23/2010

Training and Rollout

8/23/2010 - 8/30/2010

Production Support

8/30/2010 - 9/6/2010