FD - Lakewood

Project Timeline

06/16-06/26 Contract Negotiations

6/16/11 - 6/26/11

06/27/2011 - Executed Contract

06/27/2011

07/26/2011 - Internal Drawing Review #1

07/26/2011

11/10/2011 - Internal Drawing Review #2

11/10/2011

12/20/2011 - Utility Coordination With Civil

12/20/2011

Utility Coodination

01/03/2012 - Chage Of Prototype - Issued By Owner

01/03/2012

01/12/2012 - Preliminary Grades sent from Riverstone

01/12/2012

01/13/2012 - Coordination with Structural

01/13/2012

No Steel Building supplier has been selected to date.

01/13/2012 - Kowit Haults Work For FD Review

01/13/2012

Due to Civil Changes

01/17/2012 - Permit Submittal #1

01/17/2012

No Civil Coordination

01/23/2012 - Site Coordination Arch to Civil

01/23/2012

01/25/2012 - Coordination Set Sent to FDBTS

01/25/2012

02/23/2012 - City Comments

02/23/2012

Kowit had been handling City Coordination.

03/02/2012 - Permit Response #1

03/02/2012

03/16/2012 - 1st Notification of Pending Additional Services

03/16/2012

Client Notified of Additional Services

03/16/2012 - City Comments

03/16/2012

03/23/2012 - Bid Docs to Contractor @ FDBTS Request

03/23/2012

Includes Civil Drawings

04/27/2012 - 2nd Notification of Additional Services

04/27/2012

05/04/2012 - Move forward with 2012 Prototype w/o signed CA

05/04/2012

SCM directive.

05/11/2012 3rd Notification of Additional Services.

05/11/2012

Email of CA# 1,2,3 For Additional Services in PDF Format

Response - "egregious"

05/18/2012 - Meeting @ mbi|k2m

05/18/2012

05/22/2012 - Coordination with STAR Buildings

05/19/2012 - 05/22/2012

05/18/2012 Attempt To Finalize Outstanding Items

05/19/2012 - 06/01/2012

05/25/2012 - Coordinate Building Change With Civil

05/19/2012 - 05/25/2012

05/22/2012 - Email To Assign Responsible Parties for drawing scope.

05/22/2012

06/01/2012 - Permit Response #2

06/01/2012

06/11/2012 - Dropbox Coordination

06/11/2012

Most current Drawing Files Transmitted to Owners for their review

08/31/2012 - Permit Response #3

08/31/2012

09/06/2012 - Client Confirms Receipt Of Current Drawings

09/06/2012

10/15/2012 - First Contact From CORLE Buildings

10/15/2012

10/29/2012 - 10/31/2012 - Anchor Bolt Coordination

10/29/2012 - 10/31/2012

11/13/2012 - PEMB Coordination

11/13/2012

12/03/2012 - Foundation Bust - 1st Email From Contractor

12/03/2012

12/13/2012 - Reciept of Family Dollar Review

12/13/2012

01/04/2013 - Stepped Foundation Sketches Issued

01/04/2013

Contractor Still waiting on S&S drawings.

01/08/2013 - Email From Dale Ferraro - Re: Responsible Party

01/08/2013