Untitled timeline

Main

27th Floor Construction

12/21/2012 - 01/09/2013

27th floor will be the 5th floor back

New Tower

New Tower 4th Floor Offices Complete

12/13/2012 - 01/02/2013

Office will be moved:
1/2-Brenda, Eric, Sarah, & Mohammed will move
1/3-Half of Sales, Executive Offices, and Convention Services will move
1/4-Half of Sales and Catering will move
1/14-Accounting will move

Carpet Renovation

DemoCorridor Carpet Level

01/07/2013 - 01/08/2013

They will be demo carpeting south of th Prari expansion Joint

Demo Stair Carpet

01/07/2013 - 01/09/2013

Demo Pedestrian Bridge Carpet

01/07/2013 - 01/09/2013

Demo Carpet Conference Center Rooms Level 2

01/08/2013 - 01/09/2013

Paint Entrace of CC Rooms Level 2

01/09/2013 - 01/11/2013

Install Carpet CC Rooms Level 2

01/09/2013 - 01/22/2013

Install Pedestrian Bride Carpet

01/09/2013 - 01/11/2013

Wall Covering Rework Restroom Level 2

01/14/2013 - 01/16/2013

Replace Faucets

01/15/2013 - 01/16/2013

Demo Corridor Carpet North of Prairie

01/15/2013 - 01/16/2013

Install Carpet Corridor Level 2

01/16/2013 - 01/22/2013

Install New Stair Carpet

01/16/2013 - 01/18/2013

Demo Corridor Carpet Level 1

01/22/2013 - 01/23/2013

Demo Carpet CC Rooms Level 1

01/23/2013 - 01/24/2013

Paint Entrance of CC Rooms Level 1

01/23/2013 - 01/25/2013

Install Carpet Corridor Level 1

01/23/2013 - 01/29/2013

Install Carpet CC Rooms Level 1

01/25/2013 - 02/01/2013

Wall Covering Rework Restrooms Level 1

01/28/2013 - 01/30/2013

Repair Replace Light Fixture

01/29/2013 - 01/30/2013

Demo & Install Light Fixtures

01/30/2013 - 01/31/2013

Shor Restaurant

Remove Existing Carpet

01/07/2013 - 01/09/2013

Paint Wall Covering, Wall and Soffit

01/22/2013 - 01/28/2013

Install Light Fixtures

01/29/2013 - 02/01/2013

Install Woodbase

01/29/2013 - 01/30/2013

Install Restaurant Carpet

01/31/2013 - 02/04/2013

Punch Restaurant Area

01/31/2013 - 02/06/2013

Install euphostered Baquette

02/05/2013 - 02/06/2013

Repair Exisiting Host Station

02/07/2013 - 02/08/2013

M/X Lounge

Build Temp Wall

01/04/2013 - 01/07/2013

Building part of the wall on 1/4 to still have access to banana until the rest of the wall is built on 1/7 which will then have no access to the banana from 1/7 forward.

Demo Main Bar

01/11/2013 - 01/15/2013

Demo Wall /Sofit

01/11/2013 - 01/17/2013

Demo Floor Tile/Rework PLMG

01/11/2013 - 01/16/2013

Demo Back Bar

01/11/2013 - 01/17/2013

Install Quarry and Field Tile

01/22/2013 - 01/29/2013

Frame Wallat Storage

01/22/2013 - 01/28/2013

Install Main Bar

01/22/2013 - 01/28/2013

Install New Partition Inwall Rough

01/29/2013 - 02/04/2013

Install Relocate Food Service

01/29/2013 - 02/01/2013

Install Stone at Main Bar

01/29/2013 - 02/04/2013

Install Back Bar Millwork

01/30/13 - 02/05/13

Install Drywall Soffit

02/05/13 - 02/11/13

Install Stone at Back Bar

02/06/2013 - 02/07/2013

Paint & Install Wallcovering

02/12/13 - 02/18/13

Install Millwork in Bar Seating

02/12/13 - 02/18/13

Install Stone Top at Service Stations

02/19/13 - 02/25/13

Install Base & Trims

02/19/13 - 02/25/13

Install Banquettes & Tables

02/26/2013 - 03/04/13

Install New Wood Molding

03/05/13 - 03/06/13

Remove Temp Partition

03/07/13 - 03/08/13