Untitled timeline

Main

PM#2 Not on Project

PM#2 Not on Project

2 Months to Close SG2

6/24/2011 - 8/23/2011

July 2011

07/01/2011 - 07/31/2011

PM#2 Not on Project

Aug 2011

8/01/2011 - 08/31/2011

08/01/2011

PM#2: Double-Billed Time

9/1/2011 - 9/30/2011

SG2 Events

Internal Team Review - SG2

6/16/2011 - 6/23/2011

Requirements Sign-off

6/22/2011 - 6/23/2011

22-23 June: Requirements Sign-off

Requirements Walkthrough

6/22/2011

Requirements Walkthrough

SG2 Review Documented Complete

6/23/2011

SG2 Review Documented Complete

John Lead from Below

24 June: Align Program Manager & PM#1

6/24/2011

1 July: Publish Agreed Plan from Program Manager & PM#1

7/1/2011

1 July: Publish Agreed Plan from Program Manager & PM#1

5 July: Share Plan with Susan Gentile

7/5/2011

26 July: John shares SG3 Design Recommendations with PM#2

7/26/2011

25 Aug: John Emails Susan - SUCCESS - Updated Project Plan

8/25/2011

SG3 - John Recommendations

5 July: John Provides Transition Meeting to PM#2

7/5/2011

6 July: John Share Design Recommendations - PM#2

7/6/2011

6 July: John Share Program Manager Plan with PM#2

7/6/2011

26 July: John Share Program Manager Plan with PM#2

7/26/2011

9 Aug: John Share Design Recommendations

8/9/2011

SG3 - John Assignments

John Vacation

7/6/2011 - 7/25/2011

Detailed Technical Design

7/25/2011 - 8/20/2011

Test Strategy Plan

8/22/2011 - 8/26/2011

23 Aug: John - Detailed Technical Design Completed (Network)

8/23/2011

26 Aug: Test Strategy Completed

8/26/2011

29 Aug: Detailed Technical Design Uploaded Global Livelink

8/29/2011

SG3 - Events

23 Aug: John - Detailed Technical Design Completed (Network)

8/23/2011

Joint Application Design

8/31/2011

Joint Application Design

UI Design

UI Flow Analysis & Changes: Preston - D2

5/27/2011 - 6/3/2011

Change UI - D2: Preston

7/11/2011 - 7/18/2011

Mike Cross: Develop & Design EverestCardReaderForm

8/1/2011 - 8/12/2011