LTD website redesign

LTD

Research Transit District web sites

07/13/2012 - 11/26/2012

Started with contract start date, ended with Hannah providing Salem-Keizer example (although we may come across some others we want to compare with before going live)

Create new site design

08/01/2012 - 12/31/2012

Initial design for mobile, tablet, desktop - may be tweaked as we go along

Initial internal testing - devices / browsers

02/01/2013 - 03/15/2013

Iterative process - can be time-consuming, need to set limits on what we support.
Provide feedback to LCOG, make adjustments, review/test again, make adjustments, then finalize

Test with larger test group

03/22/2013 - 03/29/2013

Launch new site

04/08/2013

LCOG

Install LTD test site on LCOG internal server

09/03/2012 - 09/05/2012

Not accessible from LTD

TEST - Hastus route timetables

10/01/2012 - 11/09/2012

Set up tab look for route maps and timetable periods (weekday, Saturday, Sunday), ability to have "public" view of current season while loading "private" view of next season. Still need to add features (frozen headers, pop-up notes, highlighted columns/rows, etc.)

Review/revise scope of work

11/21/2012 - 12/14/2012

Jody/Jeff met with LTD (Andy, Russ, Craig) on 11/21 and agreed to provide more detailed scope of work - draft still in progress.

Make test site accessible to LTD

12/21/2012

Make sure public/search engines cannot view it

Implement draft site-wide elements

01/02/2013 - 01/25/2013

background, banner, footer, navigation, etc.

Front-page layout

01/07/2013 - 02/01/2013

Latest news, quick links to most popular content, other?

Implement Google Transit, other outside elements

01/14/2013 - 02/08/2013

Google Transit
Google Analytics
Constant Contact mailing lists
other?

Implement standard Drupal modules as needed for LTD implementation

01/21/2013 - 02/28/2013

TBD after design finalized

Implement special announcements

01/22/2013 - 02/28/2013

Route changes, detours, etc.

Implement route/timetable pages

01/22/2013 - 02/28/2013

Implement other LTD-specific modules (if any)

01/23/2013 - 02/28/2013

TBD after design finalized

Integrate point2point subsite

01/24/2013 - 02/28/2013

Need to determine how this will work exactly

Adjust site from test 1 feedback

03/01/2013 - 03/22/2013

Set up site statistics (Google Analytics)

04/01/2013 - 04/05/2013

Adjust site from test 2 feedback

04/01/2013 - 04/05/2013

Set up roles/permissions/logins

4/1/13 - 4/5/13

Site support/maintenance

4/8/2013 - 6/30/2013

monitor server impact
confirm backups in place
respond to any reported bugs
keep site up-to-date with critical updates
address feature requests (as budget allows)

Provide documentation/training

4/8/13 - 4/20/13

Site updates
Server/Drupal configuration
Remote server access