Digital Matter Experience - Blok M

Events

In-House Iiason (As Built coordination review, Project Standards review)

20 March 2018

2pm - 5pm,
Digital Matter be in Blok M offices for any meetings / coordination.

Session Goals:

  • Riwan + Digital Matter: review of completed As-Built
  • Donny / Riwan + Digital Matter: review of project standards for quantity takeoffs, CAD exports and simulations
  • GreaTech + Pakuwon + Digital Matter: introduction meeting with GreaTech

Submission of For-Con Drawings for Digital Matter

23 Mar 18

Date of submission was provided during Kickoff meeting. It is according to assumed timeline based on shop drawing deadline.

Notes:

  • Donny to assist in ensuring the for con Drawing for LG is submitted as priority.
  • Latest date of submission is 23 March
  • If possible, it will be submitted earlier

In-House Liason (For Con coordination review)

27 March 2018

2pm - 5pm,
Digital Matter be in Blok M offices for any meetings / coordination.

Session goals:

  • to verify any RFIs
  • to review coordination issues based on For-Con submission
  • to prioritize and focus on decisions for MEP changes before report submission

Submission of Clash Report by Digital Matter

30 Mar 18
  • 30th is latest date of submission based on For-Con submission on 23rd march.
  • Acknowledged that if possible, Digital Matter to submit report earlier
  • Digital Matter will check on 20th March in house review for any early submission of For Con drawings

Submission of Shop Drawings for Digital Matter

5 Apr 18

Date of submission was provided during Kickoff meeting and is according to existing project schedule.

Notes

  • Donny to assist in ensuring the Shop Drawing for LG is submitted as priority.

In-House Liason (shop dwg coordination review)

10 Apr 18

2pm - 5pm,
Digital Matter be in Blok M offices for any meetings / coordination.

Session Goals

  • to verify any RFIs
  • to review coordination issues based on Shop DWG submission
  • to prioritize and focus on decisions for MEP changes before report submission

Final Report

13 Apr 18

-Submission of Final Coordination report based on Shop Drawings and coordination meetings
-Submission of CAD files for Pakuwon action

Kickoff Meeting

Present