EC-12.0-Hardening Plan

Events

Scope Freeze

10 April 2018

Release branch created

All planned work is Workdone

Env Prep TC1

11 April 2018 - 18 April 2018
  • Upgrade script preparation until 10th
  • Prepare RC0 Tag
  • Test Environment preparation until 11th 1 keycloak server

Online Help Documentation

11 April 2018 - 3 May 2018

Release Documentation

11 April 2018 - 11 May 2018

Bug Quest # 1

19 April 2018

Bug Quest on upgrade Environment - Focus on new enhancements
- Explore upgrading to Data Universe and Customer Environments

Execute Automated Tests on Release Branch

19 April 2018 - 30 May 2018

TC # 1 (8 days)

20 April 2018 - 2 May 2018
  • Retest all the issues fixed for the release
  • Execute Regression Tests
  • Development

Bug Fixes (10 days)

20 April 2018 - 4 May 2018

Continue with fixes for issues seen in TC # 1

TC # 1 - Code Freeze

4 May 2018

Env Prep. TC 2

7 May 2018 - 10 May 2018

TC # 2 environments
- Create base env (25th-26th)
- RC tag made end of last day of development (26th)
- Upgrade Script amendments: From 27th - 30th (2d)
- Test environments re-establish and upgrade: Complete by 2nd May

Critical Bug Fixes (7 days)

11 May 2018 - 21 May 2018

Bug Quest # 2

11 May 2018

Penetration Testing

11 May 2018 - 14 May 2018

RC1

PO/PM X-Testing

11 May 2018 - 18 May 2018

Exploratory testing

Upgrade on 1-2 Customer Environments

11 May 2018 - 18 May 2018

Reach out to services for upgrading the 11.2.SP03 customer assets to 12.0 and get feedback.

TC # 2 (6 days)

14 May 2018 - 18 May 2018
  • Regression
  • Fixes from TC1
  • Exploratory by PO/PM

Final Code Freeze

21 May 2018

Environment Pre for BVT

22 May 2018 - 24 May 2018

BVT environments
- Create base env
- RC tag made end of last day of development (14th)
- Upgrade Script amendments: From 27th - 30th (2d)
- Test environments re-established and upgraded: Complete by 18th May

Beta Testing

25 May 2018 - 29 May 2018

Provide documentation and artefacts along with upgrade scripts to customers and start preparing for them to perform Beta Testing

TC#3 (3 days)

25 May 2018 - 29 May 2018
  • Fixes from TC2
  • Critical regression (?)
  • Build Verification Test

PO/PM Acceptance Test

25 May 2018

Verificaion of product area.

Installation and Smoke Testing

25 May 2018 - 28 May 2018
  • Manual installation testing
  • Run Automated UI tests

GNG

30 May 2018 - May 30, 2018

RELEASE

31 May 2018