Engineering Plan

Order

Receive the Order

June 1, 2018

Order received.

Confirm the Order

June 3, 2018 - June 15, 2018

Confirm the Order.

Finalize the Order

June 16, 2018

Finalize the Order.

Start Assembling

June 20, 2018

Start Assembling.

Finish part-1

June 25, 2018

Finish part-1.

Finish part-2

July 10, 2018

Finish part-2

Finish part-3

July 25, 2018

Finish part-3.

Start Packaging

August 5, 2018

Start Packaging.

Production

Manufacture the Product

June 16, 2018 - September 30, 2018

Manufacture the Product.

Delivery

Product Delivery Phase

Inspect the Product

August 5, 2018 - August 20, 2018

Inspect the Product.

Ship the Product

August 25, 2018 - September 5, 2018

Ship the Product.

Customers receive the Product

August 30, 2018 - September 10, 2018

Customers receive the Product.

Refund and Disputes

September 10, 2018 - September 25, 2018

Handle Refund and Disputes from unhappy customers.