Think!EHR - second phase

Events

Follow up

February 13, 2018 - Approx. April 24, 2018

2 MD (1 MD is done)

Data structure sync

February 13, 2018 - Approx. March 5, 2018

1 MD (DONE)

Modifying Finding Patient

Approx. February 20, 2018 - Approx. February 23, 2018

2 MD (DONE)
(It will be better if OIS with EhrID is prepared - rstefanic)

Start of development

Approx. February 20, 2018

Updating send-information procedures and functions

Approx. February 26, 2018 - Approx. April 12, 2018

2 MD (DONE)

Start testing

Approx. April 12, 2018

Test everything with Mock-data

Test and debug

Approx. April 13, 2018 - Approx. April 19, 2018

3 MD (DONE)

Preparing presentation/movie clip

Approx. April 20, 2018 - Approx. April 24, 2018

1.5 MD

Final delivery

April 24, 2018

Final version of service in this phase (new requirements can change this time)