Delhi 4D West - Monitor Timeline

Main

AFE created for $280k for 4 sqmi

08/15/2012

30 day notification to landowners

09/04/2012

Surveying for source & receiver locations

10/08/2012 - 10/14/2012

Bid accepted based on crew availability & budget

10/08/2012

Drilling for dynamite sources

10/14/2012 - 10/26/2012

Shooting the survey

10/29/2012 - 11/01/2012

Data transcribed from boxes & shipped to Houston

11/04/2012

Time-lapse results interpreted

11/19/2012

Processing completed & stacks delivered to Denbury

11/19/2012

Results examined by team during Pattern Review

11/20/2012

Results examined by team during Pattern Review

11/27/2012