This is a TImeline for project planning of the Network Upgrade before March 2013.
This is a TImeline for project planning of the Network Upgrade before March 2013.
Get network repaired so that we do not experience the issue we had last year with state testing
11/13/2012 - 11/21/2012
% complete
Contacted Ednetics, CDW, PC Mall, and Cerium requesting their assistance to do a network assessment and come back with repair options and costs.
11/21/2012 - 11/30/2012
% complete
Schedule for vendors to come down and assess our network issues.
11/30/2012 - 12/01/2012
% complete
11/30/2012 - 12/01/2012
% complete
12/3/2012 - 12/7/2012
% complete
Gather and go over any and all quotes and recommendations as provided by the vendors.
12/06/2012 - 12/07/2012
% complete
12/07/2012 - 12/08/2012
% complete
12/10/2012 - 12/11/2012
% complete
Present best option from vendor.
12/11/2012 - 12/14/2012
% complete
Start scheduling with the vendor the times for installation and repair of equipment.
12/14/2012 - 03/01/2013
% complete
Everything needs to be done by March 2013 in order to test and verify all is working before state testing starting March 25th.
02/20/2013
% complete
Get network repaired so that we do not experience the issue we had last year with state testing
12/11/2012 - 01/14/2013
% complete
If the board does not approve of original quote, then work with vendor to make appropriate changes as per recommendation by the board. Take back to board on January 14th.
01/14/2013 - 01/15/2013
% complete
Present vendor changes to the board.
01/15/2013 - 01/18/2013
% complete
Schedule installs with vendor
01/21/2013 - 03/01/2013
% complete
Everything needs to be done by March 2013 in order to test and verify all is working before state testing starting March 25th.