EC Release Plan 2018-2019

EC-12.0

Development

January 1, 2018 - February 27, 2018

Development on 12.0 scope

Technology Freeze

February 1, 2018

Changes in foundation technology are in place, although they may need some stabilizing.

Stabilizing

February 28, 2018 - March 27, 2018

Stabilization and pre-hardening activities
- scope completion (medium-low risk)
- automated regression testing
- automated and manual smoke testing
- fixing findings from automated tests

High Risk Scope Freeze

February 28, 2018

Any high risk changes to foundation technology or other deep impact business changes must be completed (Work Done) at this point.

Scope Freeze

March 27, 2018

Freeze for all planned release scope

Hardening

April 3, 2018 - May 8, 2018

Release Hardening (build Release Candidates, testing, documentation etc.)

RELEASE!

May 9, 2018

EC-12.1

Development

May 14, 2018 - October 5, 2018

Stabilizing

October 8, 2018 - October 31, 2018

Hardening

November 1, 2018 - December 4, 2018

RELEASE

December 5, 2018

Public holidays

Norway: Blue
Malaysia: Red
India: Green
International: Orange

Republic Day

January 26, 2018

Indian public holiday

Thaipusam

January 31, 2018

Malaysian public holiday

Federal Territory Day

February 1, 2018

Malaysian public holiday

Winter vacation

February 12, 2018 - February 16, 2018

Norwegian school vacation

Chinese New Year

February 16, 2018 - February 19, 2018

Malaysian public holiday

Holi

March 2, 2018

Indian public holiday

Easter

March 29, 2018 - April 2, 2018

NORWEGIAN PUBLIC HOLIDAY

Isra and Mi'raj

April 13, 2018

Malaysian public holiday

Labour Day

May 1, 2018

International Labour Day

Ascention Day

May 10, 2018

Norwegian Public Holiday

Ramadan begins

May 16, 2018

Malaysia

Constitution Day

May 17, 2018

Norwegian National day

Pinse

May 21, 2018

Norwegian Public Holiday